De-shuttering time of formwork

Soffit formwork to slab=3days
Soffit formwork to beam=7days
Beam up to 4.5m span=7days
Beam over 4.5m span=14days
For footing formwork =16hours to 20hours
Stair case formwork=5days
Spanning up to 6m beam=21days