Featured Post

Civil engineering job in ROYAL GROUP SYSTEM

site/planning/estamination planing, designing, development and manage projects for the construction or repair of buildings, roads. Execu...

Saturday, July 21, 2018

Civil Engineering

De-shuttering time of formwork

Soffit formwork to slab=3days
Soffit formwork to beam=7days
Beam up to 4.5m span=7days
Beam over 4.5m span=14days
For footing formwork =16hours to 20hours
Stair case formwork=5days
Spanning up to 6m beam=21days

No comments:

Post a Comment